Brit Oval: Floodlights Programme

Dear Neighbour,

As part of our ground improvement programme, we are installing permanent floodlights at the Brit Oval. Please find enclosed a programme of works beginning on January 5th 2009.

While the programme sets out the expected timeframes, it may be that dates or orders of activity are adjusted as it moves forward. The plan will be updated on a regular basis and if any major changes to the programme are anticipated we will ensure that you are notified as soon as possible.

If you have any enquiries, please contact community@surreycricket.com

Best wishes

Steven Blackwood,

Community Executive

The Brit Oval

Floodlights project programme

The following is an outline programme of works relating to the installation of the four mast floodlighting system at The Brit Oval. It will be updated on a monthly basis in an attempt to ensure that it is as accurate as possible.

Mast 1 – refers to the mast behind the OCS in front of Oval Mansions

Mast 2 - refers to the mast behind the OCS next to the Alex Stewart Gate

Mast 3 - refers to the mast behind the Bedser Stand.

Mast 4 - refers to the mast behind the Lock/Laker stand

Activity

Approximate location

Start

Finish

Comment

Piling prep for mast 1

Behind OCS in front of Oval Mansions

Jan 5

Jan 12

Moving equipment into the area

Piling prep for mast 2

Behind OCS stand by Alex Stewart Gate

Jan 12

Jan 19

Moving equipment into the area

Piling prep for mast 3

Bedser Stand

Jan 19

Jan 26

Moving equipment into the area

Piling prep for mast 4

Lock/Laker Stand

Jan 26

Feb 2

Moving equipment into the area

Piling for mast 1

Behind OCS in front of Oval Mansions

Jan 12

Jan 26

Drilling pile – relatively little disturbance

Piling for mast 2

Behind OCS stand by Alex Stewart Gate

Jan 19

Feb 2

Drilling pile – relatively little disturbance

Piling for mast 3

Bedser Stand

Jan 26

Feb 9

Drilling pile – relatively little disturbance

Piling for mast 4

Lock/Laker Stand

Feb 2

Feb 16

Drilling pile – relatively little disturbance

Pile Caps/make good 1

Behind OCS in front of Oval Mansions

Jan 19

Feb 9

Constructing and concreting base – relatively little disturbance

Pile Caps/make good 2

Behind OCS stand by Alex Stewart Gate

Jan 26

Feb 16

Constructing and concreting base – relatively little disturbance

Pile Caps/make good 3

Bedser Stand

Feb 2

Feb 23

Constructing and concreting base – relatively little disturbance

Pile Caps/make good 4

Lock/Laker Stand

Feb 9

Mar02

Constructing and concreting base – relatively little disturbance

Lighting installation Head frame 1

Behind OCS in front of Oval Mansions

Jan 5

Jan 17

Construction of Head Frame

Lighting installation Head frame 2

Behind OCS stand by Alex Stewart Gate

Jan 17

Jan 29

Construction of Head Frame

Lighting installation Head frame 3

Bedser Stand

Jan 29

Feb 12

Construction of Head Frame

Lighting installation Head frame 4

Lock/Laker Stand

Feb 12

Feb 26

Construction of Head Frame

Install pedestal/mast/head frame 1

Behind OCS in front of Oval Mansions

16 Feb

19 Feb

Crane and mast located in the ground – mast lifted into location

Install pedestal/mast/head frame 2

Behind OCS stand by Alex Stewart Gate

23 Feb

27 Feb

Crane and mast located in the ground – mast lifted into location

Install pedestal/mast/head frame 3

Bedser Stand

02 Mar

05 Mar

Crane located on road – mast inside ground – mast lifted into position

Install pedestal/mast/head frame 4

Lock/Laker Stand

09 Mar

12 Mar

Crane and mast located in the ground – mast lifted into location

Test and check mast 1

Behind OCS in front of Oval Mansions

23 Feb

25 Feb

Test and check mast 2

Behind OCS stand by Alex Stewart Gate

02 Mar

05 Mar

Test and check mast 3

Bedser Stand

09 Mar

12 Mar

Test and check mast 4

Lock/Laker Stand

16 Mar

19 Mar

Trenching and cabling

Mast 1 to Alex Stewart Gate

05 Jan

12 Jan

Small digger to create trench

Trenching and cabling

Mast 2 to Alex Stewart Gate

13 Jan

20 Jan

Small digger to create trench

Trenching and cabling

Mast 2 to mast 3

21 Jan

29 Jan

Small digger to create trench

Trenching and cabling

Mast 3 to Pavilion

29 Jan

11 Feb

Small digger to create trench

Trenching and cabling

Pavilion to Loch Laker

12 Feb

17 Feb

Small digger to create trench

Trenching and cabling

Behind Lock/Laker to Mast 4

18 Feb

29 Feb

Small digger to create trench

Testing

All masts

06 Apr

May

Mostly daytime